UER: Bolgatanga -Bawku- PolimKom road Supplementary Agreement Cost 127M Euros.

The preliminary contract sum for the Upper East Region stretch of the Bolgatanga-Bawku-Pulmakoum road project was pegged at GH¢ 613 million when it was awarded to two contractors; Mawums Construction Limited, a Ghanaian company, and Queiro Galvao, a Brazil contraction firm.

The two contractors withdrew their equipment from the project site for close to a year due to non-payment of arrears. speaking to the resident engineer, Chief Peter Dagadu on the ‘Word Community Watch’ a daily radio program on a Zuarungu based local Radio station, Word FM, he disclosed that about 127 million euros which is equivalent to Eight hundred and fifty million, two hundred and fourteen thousand and two hundred Ghana cedis Gh 850214200 supplementary agreement cost has so far been approved for the project.

Construction works on the bridge along the Tilli forest stretch.

In March 2020, a sum of €139.4 million was approved by Parliament to finance the construction of phase one of the Bolgatanga-Bawku-Polimakom road.

The amount was to be provided by HSBC Bank and KEW IPEX Bank GmbH. Under the credit arrangement, the HSBC Bank Plc., United Kingdom will lend a total of up to €68,000,000.00 and km IPEX GmbH will also lend up to €72,000,000.

The agreements were presented to parliament on March 24, 2020 by the Minister of Parliamentary Affairs, Osei Kyei-Mensah-Bonsu on behalf of the Minister of Finance, and were approved by the House.

Portions of the completed section of the road

The resident engineer told word news that there is another provision for the Bolgatanga- Bawku -Pulimakom road project due to some changes that has been affected on the entire project. “in the supplementary agreement, there is another provision made for the project, is 127 million euros for the project , that is what made , well in road construction it’s nothing that is what will complete the work, for instance Bolga town dual carriage is 2km ad its ends two, three meters off the bridge so there is the need to extend I feather that, will be an additional cost, earlier on 6km provision was made for Bawku bypass as we speak now it’s now 15km but in the contract it was 6 km so all these will be an additional cost “ Mr Peter Dagadu .

Source: mywordfmonline.com/Gaspard Ayuureneeya

Share this article

Leave a Reply

Your email address will not be published. Required fields are marked *

DzRxEk70 Lasting Longer In Bed A Realistic Look At Male Enhancement Procedure Ld | J96EsKbv Blue Chews Review How Real Men Are Finding Lasting Satisfaction Qm | MQKoC3 Realistic Results How To Improve Male Enhancement Naturally Without Scams Je | 7cKxlo0s How To Improve Male Sexual Health Without Overlooking The Basics 7j6 | WcodFA Male Cosmetic Enhancement Dedham The Secret To Boosting Libido And Stamina Vxs | Am7QEzt How Daily Vitamins Can Transform Your Confidence And Intimacy Cl | 5l9qd Do Rhino Pills Actually Work A Realworld Guide To Understanding Their Impact On Male Health Ern | YzMn Beast Super Test The Ultimate Male Enhancement Solution You Need To Know About Cy | Bbt6wU How Super Male Vitality Drops Help Men Regain Control Over Their Sexual Health Zsf | NYFOr Natural Remedies For Boosting Male Vitality How Herbs Enhance Performance And Stamina X4 | ZAuTX How To Improve Erectile Strength Without Scams A Realistic Guide For Men Sx8 | IiREgz Primal Lift Male Enhancement Real Stories Real Results Ay | 19AFzOE How Blood Flow Supplements Can Transform Your Intimacy Without The Pressure Of Size Or Stamina G2 |