UER: Bolgatanga -Bawku- PolimKom road Supplementary Agreement Cost 127M Euros.

The preliminary contract sum for the Upper East Region stretch of the Bolgatanga-Bawku-Pulmakoum road project was pegged at GH¢ 613 million when it was awarded to two contractors; Mawums Construction Limited, a Ghanaian company, and Queiro Galvao, a Brazil contraction firm.

The two contractors withdrew their equipment from the project site for close to a year due to non-payment of arrears. speaking to the resident engineer, Chief Peter Dagadu on the ‘Word Community Watch’ a daily radio program on a Zuarungu based local Radio station, Word FM, he disclosed that about 127 million euros which is equivalent to Eight hundred and fifty million, two hundred and fourteen thousand and two hundred Ghana cedis Gh 850214200 supplementary agreement cost has so far been approved for the project.

Construction works on the bridge along the Tilli forest stretch.

In March 2020, a sum of €139.4 million was approved by Parliament to finance the construction of phase one of the Bolgatanga-Bawku-Polimakom road.

The amount was to be provided by HSBC Bank and KEW IPEX Bank GmbH. Under the credit arrangement, the HSBC Bank Plc., United Kingdom will lend a total of up to €68,000,000.00 and km IPEX GmbH will also lend up to €72,000,000.

The agreements were presented to parliament on March 24, 2020 by the Minister of Parliamentary Affairs, Osei Kyei-Mensah-Bonsu on behalf of the Minister of Finance, and were approved by the House.

Portions of the completed section of the road

The resident engineer told word news that there is another provision for the Bolgatanga- Bawku -Pulimakom road project due to some changes that has been affected on the entire project. “in the supplementary agreement, there is another provision made for the project, is 127 million euros for the project , that is what made , well in road construction it’s nothing that is what will complete the work, for instance Bolga town dual carriage is 2km ad its ends two, three meters off the bridge so there is the need to extend I feather that, will be an additional cost, earlier on 6km provision was made for Bawku bypass as we speak now it’s now 15km but in the contract it was 6 km so all these will be an additional cost “ Mr Peter Dagadu .

Source: mywordfmonline.com/Gaspard Ayuureneeya

Share this article

Leave a Reply

Your email address will not be published. Required fields are marked *

Williams 1 Secret How Lima Beans Turbocharge His Weight Loss | Remi Bader Weight Loss Personal Ozempic Journey Detailed | Kelly Clarksons Weight Loss What OTC Product Made the Difference | Zion Williamson Weight Loss How Conditioning Impacts His Defensive Role | Tamela Mann Weight Loss A Guide to What We Know Right Now | John Goodmans Remarkable Weight Loss I Wish I Knew This Sooner A Nod to Keto ACV Gummies | Nicole Byer Weight Loss Latest 2025 Update and Health Journey | How Does Alicia Silverstone Stay So Fit Hint Its Her Healthy Weight Loss Breakfast with Eggs | Your Guide to Weight Loss Understanding Pills With a Nod to Jazz Jennings Resilience | Melissa ONeil Weight Loss Current Pics And Fitness Journey | Did John Goodman Opt for Weight Loss Surgery Get the Full Scoop | Scott Jennings weight loss The surprising reason he changed his diet plan and workout routine | Brendan Fraser weight loss news confirms actor lost 40 lbs following strict healthy lifestyle | Lose 10 Lbs in 2 Weeks We Tried the Tiffany Haddish Weight Loss Diet | Unlock Your Potential Cushing Syndrome Weight Loss Before After Motivated by Natalie Portman | Leslie Appleyards Top 5 Tips for Accelerated Abdominal Weight Loss |